◆Complete Set Configuration:Hydraulic lifting and lowering system for segment tensioning at high position
◆Lowering system:continuouse strand jack + steel strand
◆Jack up force: 300t×4
◆Jack up height:Max.4000mm
◆Jack up speed:0-6m/hr
◆Control method:Manual operate valve
◆Pump station:2 sets
◆Pump Motor:11kw×4sets
◆Lowering system moving system:
Travel speed:8.7m/min(no load)、Travelling Motor:1.1kw×4sets
◆Total power:50kW
◆Total weight:2×24t